Contractor Non-Performance in Quebec: What the Law Says

When a contractor stops work or abandons a project mid-build, the owner is left with incomplete construction work, money already paid, and no clear path forward. Contractor non-performance in Quebec is a defined legal concept under the Civil Code of Quebec, and owners have specific remedies when it occurs. The steps you take, and the order in which you take them, determine how much you can recover and how quickly the project can move forward.

Construction contracts in Quebec are governed by the Civil Code of Quebec (CCQ) as contracts of enterprise, meaning agreements under which a contractor undertakes to carry out physical work for a client in exchange for compensation.

That legal category matters because it triggers a specific set of obligations. Under art. 2100 CCQ, every contractor is bound by three baseline duties regardless of what the contract says:

The standard that governs most physical construction work is the obligation of result (obligation de résultat). Under this standard, the contractor doesn’t just have to try; they have to deliver. A contractor bound by an obligation de résultat can only escape liability by proving force majeure: an event that was unforeseeable, irresistible, and external to their control.

  • Showing that the project was difficult, that costs exceeded expectations, or that scheduling was complicated is not enough to escape liability.
owner and contractor dispute over contractor non-performance

What Counts as Non-Performance Under Quebec Law

Non-performance is one of several types of construction disputes that owners and contractors face under Quebec civil law, and it covers a range of situations: a contractor who has walked off the job and won’t return, one who has been absent for weeks without explanation, and one who claims the work is finished when it plainly isn’t.

Which category a situation falls into determines which remedy path is available, what notice is required before pursuing it, and how a court will assess the value of work completed to that point.

Abandonment, Delay, and Defective Work

SituationHow it arisesEffect on remedies
AbandonmentThe contractor has stopped work and made clear, through explicit statement or conduct, that they won’t be returning. The contract has effectively been repudiated.Strongest basis for resiliation as a sanction and a full cost-of-completion damages claim. Default is often clear without extended notice periods.
DelayThe contractor is still nominally on the job but mobilization is inconsistent and progress has stalled. Whether it crosses into actionable non-performance depends on the contract’s schedule provisions and whether any justification has been offered.Requires careful documentation of the timeline before sending formal notice. Remedy path depends on whether the delay is total or partial.
Defective or incomplete workThe contractor considers the work finished; the owner disputes whether it conforms to the contract and trade standards. Often involves scope disagreements rather than a refusal to perform. For a detailed look at this specific problem, see our article on defective construction work.Payment reduction and expert assessment are the primary tools. Resiliation is less commonly the right path since the contractor has purported to complete the work.

Thinking about hiring a replacement contractor?

We help owners document incomplete work, assess their legal remedies, and build the strongest possible claim for the additional costs of completing the project.

How to Put a Contractor in Default in Quebec

In most cases, triggering the legal remedies available under the Civil Code of Quebec requires first putting the contractor formally in default. This is done through a mise en demeure, a formal written notice that identifies the contractor’s obligations, describes the default, and sets a reasonable deadline for the contractor to perform or respond.

The mise en demeure is not just a practical courtesy. Under art. 1590 CCQ, a creditor’s remedies for non-performance, including the right to force performance, resiliate the contract, or claim damages, are available once the debtor is in default. In most construction non-performance situations, the mise en demeure is what puts that process in motion.

The notice must:

  • Identify the specific obligations the contractor has failed to perform
  • Describe the nature and extent of the default clearly
  • Set a deadline that is reasonable given the nature of the work and circumstances
  • State that failure to comply will result in legal proceedings without further notice

The deadline question matters. Quebec courts have held that the creditor must allow sufficient time for the debtor to actually perform, taking into account the complexity of the remaining work. Setting an unreasonably short deadline can undermine the notice’s legal effect.

When Formal Notice Isn’t Required

There are situations where a contractor is in default by operation of law (en demeure de plein droit) without any notice being required. Under art. 1597 CCQ, this occurs when:

  • The obligation could only have been performed within a specific time period that has now passed
  • The contractor has clearly and explicitly stated they will not be performing
  • The contractor has, through their own fault, made performance impossible
  • In a successive-performance context, the contractor has repeatedly refused or neglected to perform

In practice, even where ipso jure default arguably applies, construction lawyers in Quebec routinely recommend sending a formal notice anyway. It creates a clear documentary record, establishes the exact date from which default is measured, and demonstrates good faith, which courts expect of both parties throughout a dispute.

What Happens if the Contractor Doesn’t Respond

Once the deadline in the formal notice passes without performance or a substantive response, the owner’s remedies under art. 1590 CCQ are fully activated. This is the moment to document the state of the work thoroughly: dated photographs, a written description of what is complete and what is not, any communications from the contractor, and any records of progress payments made. This documentation is the evidentiary foundation for every subsequent step: a negotiated resolution, an expert assessment, or court proceedings.

owner deaing with non responsive contractor on construction site dispute Contractor non-performance

Remedies Available to the Owner

Once the contractor is in default, art. 1590 CCQ gives the owner three core options: force performance of the obligation, resiliate the contract and adjust their own payment obligation accordingly, or claim damages. A contractor breach of contract in Quebec can support all three paths simultaneously, though the remedy chosen shapes what the owner owes and what they can recover. These aren’t mutually exclusive: an owner can resiliate the contract and claim damages simultaneously, as long as the damages claimed reflect actual losses rather than an attempt to double-recover.

Contractor non-performance in Quebec doesn’t automatically mean the owner walks away whole. The outcome depends on which remedy is pursued, how it’s documented, and whether the owner takes steps to minimize their own losses after the contractor defaults.

Resiliating the Contract

An owner can resiliate a contract of enterprise in two ways.

  1. The first is as a unilateral right under art. 2125 CCQ: a client may resiliate a contract of enterprise at any time, even while work is in progress, without having to prove fault. This right is not of public order, meaning the parties can contract out of it, but only through a clear, express, and unequivocal waiver.
  2. The second path is resiliation as a sanction: terminating a construction contract under Quebec law where the contractor’s fault is the basis. This route follows arts. 1590, 1602, 1604, and 1605 CCQ. The owner must establish the contractor’s default, and the formal notice process described above is part of that chain.

    The advantage of the sanction route is that it grounds the owner’s damages claim directly in the contractor’s fault, which matters for what the owner can recover beyond the cost of incomplete work.

The practical difference between these two paths affects what the owner owes the contractor for work completed up to the point of resiliation. Under the unilateral route, compensation is governed by art. 2129 CCQ: the owner pays for actual costs, expenses, and the value of work performed. Under the sanction route, the owner’s payment obligation is assessed in light of the contractor’s fault, and damages can offset what would otherwise be owed.

Do You Still Have to Pay for Incomplete Work?

No, not in full. Under art. 1591 CCQ, if a contractor fails to perform their obligations to a substantial degree, the owner may reduce their payment obligation proportionally to what was actually delivered.

What determines how much you owe:
The value of work performed to that point. Where the parties can’t agree on that figure, art. 2112 CCQ allows a court to appoint an expert to assess the work and quantify the amounts — that assessment becomes the basis for determining what portion of the contract price remains payable.

Where disputed invoices come in:
This is the moment contractors typically submit a final invoice that doesn’t reflect the incomplete state of the project. An expert assessment under art. 2112 CCQ gives both parties an objective foundation for resolving that disagreement — and is often what makes or breaks a disputed invoice claim. LINKED

Claiming the Cost of Completion

When a contractor abandons a project, the owner generally has the right to hire a replacement contractor to complete the work and claim the additional cost as damages for non-performance against the defaulting contractor. This is one of the most direct forms of recovery available in a contractor non-performance Quebec situation.

The damages claim covers the difference between what it cost to complete the project with the replacement contractor and what would have been owed to the original contractor had they finished the work. The owner is expected to take reasonable steps to mitigate their losses, as courts in Quebec won’t award damages for costs the owner could have avoided through reasonable action. Letting the project sit idle indefinitely while the claim develops is not considered mitigation.

Documentation requirements for this type of claim:

  • The original contract and any change orders or scope documents
  • Records of all payments made to the original contractor
  • The formal notice and any communications following it
  • The replacement contractor’s contract and invoices
  • Photographs documenting the state of work at the time of abandonment and upon completion
  • Any expert assessments or professional reports

How Ponce & Associés Helps Owners Facing Contractor Non-Performance

Ponce & Associés represents owners dealing with contractor non-performance across residential, commercial, and institutional construction projects in Quebec. The firm’s practice in construction law is built around the specific mechanisms of the Civil Code of Quebec, not general litigation principles applied to construction facts.

In contractor non-performance situations, we assist with:

  • Reviewing the contract to identify the applicable obligations and default provisions
  • Drafting and sending the formal notice (mise en demeure) to put the contractor in default correctly
  • Advising on which remedy path (forced performance, resiliation, or damages) best fits the situation and the client’s objectives
  • Initiating or responding to expert assessment processes under art. 2112 CCQ
  • Negotiating with the defaulting contractor or their insurer to reach a resolution without court proceedings
  • Representing owners in litigation when negotiation fails

Our firm represents owners throughout Quebec, helping clients preserve their rights, respond to disputes strategically, and protect their legal position before deadlines and procedural requirements limit their recourse.

Your next steps after a contractor defaults matter.

Every decision can affect your ability to recover damages. Ponce & Associés can help you protect your position before costly mistakes are made.

Frequently Asked Questions

Conclusion

Contractor non-performance in Quebec gives owners real remedies, but those remedies depend on the right steps taken in the right order. The mise en demeure, the remedy path, and the documentation behind it all shape what you can recover. If your contractor has stopped work or abandoned the project, legal advice at the outset is what protects your position.